Operational performance
Capacity added in FY 2024-255
O&M availability
Plant load factor (PLF) achieved in FY 2024-25
Despatch performance achieved inFY 2024-25
Contracted Power Purchase Agreement (PPA) Sales volume mix achieved during FY 2024-25
Merchant / Short Term
Plant Load Factor (PLF) during FY 2024-25 (vs 55.4% during FY 2023-24)
uptime for Unit 4 (330 MW capacity) sub-critical technology
uptime for Unit 7 (660 MW capacity) supercritical technology
National uptime record achieved till September 2020
Capex incurred for improvement in safety, reliability, equipment availability, operational efficiency
Expected break-even for applicable capex activities
Capex planned to reduce overhauling time which includes:
Plant Load Factor (PLF) during FY 2024-25, (vs 73.3% during FY 2023-24)
O&M availability
Capex incurred for activities including reliability, availability, as well as efficiency improvement initiatives
Expected break-even for applicable capex activities
Plant load factor (PLF) during FY 2024-25 (vs 76.6% during FY 2023-24)
Capex incurred for reliability, availability as well as efficiency improvement
Expected break-even for applicable capex activities
Automatic release of the access control gate at service building in case of fire, through digital communication between Fire Alarm System PLC and Security access control system
Real-time video analytics-based application to detect person without arc flash suit and disseminate safety alert message
Analytical approach for prediction of CT fills chocking for timely initiation of actions, thereby reducing the impact plant performance
Digitalisation of measurement using ultrasonic sensors for real-time monitoring
Plant load factor (PLF) during FY 2024-25 (vs 53.7% during FY 2023-24)
Achieved on account of strict compliance of ZFO & RCA recommendation points
Achieved through implementing U2 APH Basket Replacement, NDCT fills replacement, etc.
Capex incurred for activities including reliability, availability, as well as efficiency improvement initiatives.
Adani Power Udupi has implemented several AI, ML, and Robotic Process Automation initiatives. These projects have significantly enhanced operational efficiency, optimised resource utilisation, and fostered innovation across departments.
A machine learning model, to recommend optimal setpoints. It optimises various boiler performance parameters while considering operational constraints.
Developed using Principal Component Analysis (PCA), this tool estimates soot accumulation. It improves heat gain in individual zones, enhancing the heat rate.
Recommends optimal mill combination before load changes to ensure efficient mill operation during load variations.
An AI-driven safety system for detection of arc-flash suit, during HT/LT breaker isolation or normalisation, mitigating electrical safety risks.
A safety alert system designed to detect approaching trains/rakes, safeguarding workers during track maintenance or cleaning activities

Plant Load Factor during FY 2024-25 (vs 72.2% in FY 2023-24)
Capex dedicated for
Break-even tenure for applicable capex projects
Replaced both APH hot-end baskets during COH to address high DP across flue gas and primary air, significantly improving heat rate and overall efficiency
Replaced 3,400 m³ of NDCT fills during COH to enhance cooling performance, leading to improved heat rate and operational efficiency
Installed hot and cold air gates in two coal mills to safely isolate leakage areas, enabling maintenance without complete shutdowns and improving equipment availability
Implemented an online DGA system for real-time monitoring of transformer oil, providing early fault detection and enhancing transformer reliability and maintenance efficiency
Plant load factor during FY 2024-25 (vs 75.4% during FY 2023-24)
PLF achieved in April 2024, surpassing the previous best PLF figures 98.3% in March 2022
Achieved in all India PLF during the first quarter FY 2024-25
Two Adani Power Raigarh Teams Qualified for Final Presentations
Capex incurred for the following activities:
Expected break-even tenure for applicable capex projects
Deployed real-time safety dashboards for performance tracking and informed decision-making
Integrated Asset Health Index via Aveva PI to monitor and compare critical equipment performance in real time
Plant Load Factor (PLF) during FY 2024-25 (vs 63.9% during FY 2023-24)
Condenser Vacuum Improvement
Major capex projects adhered during FY 2024-25:
Plant load factor (PLF) during FY 2024-25 (vs 63.3% during FY 2023-24)
Expected capex incurred for reliability, availability as well as efficiency improvement i.e.,
Expected break-even tenure for applicable capex projects
Enabled real-time data analysis and operational modelling, enhancing efficiency and performance optimisation
Standardised processes and optimised resources, driving operational excellence across the plant
Strengthened safety practices with strict adherence to protocols, effective monitoring, and continuous improvement
Improved operational efficiency, accountability, and performance through structured monitoring and evaluation
Integrated operational excellence initiatives to enhance problem-solving capabilities within teams
Plant load factor (PLF) during FY 2024-25
Capex planned for improvement in safety, reliability, equipment availability, operational efficiency as well as to reduce overhauling time
Plant load factor (PLF) during FY 2024-25
Capex planned for improvement in safety, reliability, equipment availability, operational efficiency as well as to reduce overhauling time

Plant load factor (PLF)
during FY 2024-25
That installed a Flue Gas Desulphurisation
(FGD) unit with 100% capacity
ADTPS plans key capital expenditure projects to sustain performance and extend asset lifespan. To achieve 100% ash utilisation, it will install a clinker grinding unit to convert ash waste into a useful product.
Capex planned for improvement in safety, reliability, equipment availability, operational efficiency as well as to reduce overhauling time